JULY 21,2025

BASF Achieves Mechanical Completion for Acrylics Complex at Zhanjiang Verbund Site

Hz info2025-07-21 17:06

n  Mechanical completion reached for Glacial Acrylic Acid (GAA) and Butyl Acrylate (BA) plants

n  World-scale facilities are on track for commissioning and start-up in 2025

Hong Kong SAR, China – July 21, 2025 – BASF has reached a major construction milestone at the Zhanjiang Verbund site with the successful mechanical completion of the first batch of plants in the acrylics complex, including the glacial acrylic acid (GAA) and butyl acrylate (BA) plants. This achievement marks a significant step toward the site’s scheduled start-up in 2025, further strengthening BASF's position as a global leader in the acrylics market.

12.png

BASF marks the successful mechanical completion of the glacialacrylic acid (GAA) and butyl acrylate (BA) plants at the Zhanjiang Verbundsite.

“The acrylics business has been a cornerstone of BASF Petrochemicals. With the completion of the new acrylics complex in Zhanjiang, we are further enhancing our production capacities along the acrylics value chain,” said Bir Darbar Mehta, Senior Vice President of Petrochemicals Asia Pacific at BASF. “These new world-scale production facilities will allow us to meet the fast-growing demand for acrylics in China and across Asia with a reliable supply of high-quality, competitive products and shorter lead times.”

"Since breaking ground in 2023, our team has been committed to upholding the highest safety and quality standards throughout construction and mechanical completion while achieving excellent progress,” said Han Liang, Vice President of Industrial Petrochemicals Operations for Petrochemicals Asia Pacific at BASF. “We have now moved into the commissioning and start-up phase, and we are confident in commencing operations in 2025, delivering superior value to our customers across the region.”

Acrylic acid is an important precursor for the production of superabsorbent polymers. Butyl acrylate, an ester of acrylic acid, is widely used in the production of adhesives, architectural coatings, and industrial coatings. The acrylics complex at the Zhanjiang Verbund site is planned to come on stream by 2025, with an annual production capacity of approximately 400,000 metric tons of BA.

Background information on BASF’s new Verbund site in Zhanjiang

The Zhanjiang Verbund site will be BASF’s largest investment to date with around €10 billion upon completion. It will be operated under the sole responsibility of BASF and will be the company’s third-largest Verbund site worldwide, following Ludwigshafen, Germany, and Antwerp, Belgium.


DisclaimerThe Institute of Plastic Research makes every effort to ensure the accuracy of the information, reliability of the data, and objectivity and fairness of the content and viewpoints described herein. However, we do not guarantee the accuracy and completeness of the information. Any losses or legal consequences resulting from actions taken based on this information are the sole responsibility of the individual undertaking them.

Media Contact

Luke
Head of Info Center

Release product requirements

Product Description
Quantity
Mailbox
Contact Name
Address
Company Name
Telephone No
Message

0/2000